How do I get a building permit in Los Angeles?

In the City of Los Angeles you apply to the Department of Building and Safety at dbs.lacity.gov. Simple work is permitted at the counter or online the same day. Anything structural, or anything needing zoning review, goes through plan check, which takes weeks to months. Beverly Hills, Santa Monica, Pasadena and the other independent cities run their own departments.

Permit review time by project typeA bar chart of typical Los Angeles plan review times. Simple permits take days, a pre-approved standard plan ADU three to ten business days, a custom detached ADU eight to fourteen weeks, and a new house nine to eighteen months from design to permit.Water heater, panel, reroofSame day to a weekPre-approved standard plan ADU3 to 10 business daysKitchen or bath with drawings2 to 6 weeksGarage conversion ADU6 to 10 weeksCustom detached ADU8 to 14 weeksAddition under 500 sq ft6 to 12 weeksNew house, design to permit9 to 18 monthsWEEKS OF FIRST REVIEW · CITY OF LOS ANGELES
Review time by project typeA complete ADU application has a hard 60-day decision deadline. Nothing else on this chart does.
Which department you are even dealing with

The City of Los Angeles covers Hollywood, most of the Valley, the westside neighborhoods inside city limits, South LA and the Harbor. Beverly Hills, West Hollywood, Santa Monica, Culver City, Pasadena, Burbank, Glendale, Long Beach and the beach cities each have their own. Unincorporated areas go to LA County Public Works. Mailing addresses mislead constantly, so we confirm jurisdiction by parcel, not by what the envelope says.

The fast lane

Reroofs, water heaters, panel upgrades, like-for-like window swaps, small electrical and plumbing work, and some kitchen and bath remodels can be permitted online or at the counter, often the same day or within a week. If your project fits a pre-approved standard plan, as many ADUs do, plan review can come back in 3 to 10 business days.

The slow lane

Additions, ADUs, structural changes, new construction and commercial work all need a full drawing set. The city reviews for building code, zoning, grading, fire, and sometimes planning and public works. A residential addition commonly takes 6 to 12 weeks for a first review and each correction round adds a few weeks. A complete, clean first submittal is the only part of this you control, and it is worth a lot.

Fees

Permit fees are based on the project valuation. Additions and new units also pay school district fees per square foot, and some projects pay sewer, park and dwelling unit fees on top. We put the known fees in the estimate rather than letting them show up later as a surprise.

Los Angeles County figures, reviewed 2026-10-29 by America General Contractors, California contractor licence CSLB 1083262. Planning ranges, not a quote, and not legal advice. We confirm the current rules for your parcel before anything gets drawn.

Related questions

Who does this work

Let's talk about your property.

Call, or send the address and what you want to do. We will walk it, confirm what the city allows, and send a written proposal with scope, cost and timeline.

(310) 734-2245Monday to Friday, 8am to 6pm · CSLB 1083262